BOLT: Multi-Bottleneck Bound-Guided Learning for Flexible Job-Shop Scheduling with Time Lags and Resource-Coupled Transport

arXiv机器学习 2026-10-15 16:54 3 阅读 查看原文

Flexible job-shop scheduling becomes resource-coupled when a scarce vehicle fleet moves jobs between stations, because the schedule sets the transport waits.

BOLT (bound-oriented learning for transport-coupled scheduling) builds a lower bound from chain, machine-capacity, and fleet-capacity relaxations.

The bound equals the makespan at termination, so its per-step changes form a reward that sums to a constant minus the makespan.

Because it never exceeds the attainable makespan, each candidate's bound increase is a proven rise of the makespan floor, which the policy reads as a price.

The root bound certifies a completed schedule's suboptimality gap without a solver.

On industry-motivated 10-module prefabricated-construction instances

On industry-motivated 10-module prefabricated-construction instances, explicit transport coupling outperforms a transport-penalty policy in every tested cell where loaded moves occupy at least 66% of fleet time and in none at or below 56%.

Across five zero-shot 50- and 80-module production batches

Across five zero-shot 50- and 80-module production batches, BOLT outperforms the best dispatching-rule pair on four and the penalty policy on the three with long moves.

In the three-vehicle 80-module batch, its mean makespan is 13.0% below the best pair and 4.2% below an hour-budget constraint-programming solver whose proven gap averages 34%.

BOLT's performance

BOLT decides in 2.3-5.9 ms per event on one processor core and re-plans a disruption in seconds.